Construction Update – July 24, 2022

Utility Line Location

Our construction teams will begin potholing for utilities on Monday, July 25th. Potholing for utilities is the process of finding utility lines and their locations before construction or excavation work takes place in accordance with IVGID requirements.

The potholing will occur on Stateline Avenue, Reservoir Road, and Lakeview Avenue. Work will be completed generally one location at a time with limited impact on the traffic. Roads will occasionally be single lanes for approximately 100 feet to 200 feet. Construction flaggers will assist with traffic flow during the potholing operations.

If you have any questions, please call Mike Dunn at 775.901.6633

Impacted Areas
Stateline Avenue, Reservoir Road, and Lakeview Avenue

Start Date
Monday, July 25th

Times
7:00am – 4:00pm

Estimated Duration
2 Weeks