Construction Update – August 12, 2022

Site Work & Demolition

Site work continues to progress at the Tahoe Biltmore site. Starting Friday, August 12, demolition and removal of the old storage containers and trailers on the property will begin. Once completed, demolition of select buildings, their foundations, and site clean-up will commence. There will be no road closures.

If you have any questions, please call Mike Dunn at 775.901.6633.

Impacted Areas
Wassou and Reservoir Roads

Start Date
Friday, August 12th, 2022

Times
7:00am – 4:00pm

Estimated Duration
3 Weeks